photo Nurito - Beritajakarta.id

Contractor Targets to Finish Cilangkap Reservoir Dredging Work in November

Dredging is carried out to four meters depth

The 5-hectare Cilangkap Reservoir dredging work, which is located in RW 01 Cilangkap, Cipayung, East Jakarta has currently touched 30 percent and is targeted to be complete in the forthcoming November.

Clay Dredged from Munjul Reservoir Used to Expand Burial Ground at TPU Bambu Apus

It has two cross sections and is located on the border of Cilangkap and Munjul urban villages.

East Jakarta Water Resources (SDA)'s Maintenance Division Head, Puryanto said, as many as four heavy equipment had been alerted to the location, consisting of three heavy equipment type standard and one unit of long arm.

"Dredging is carried out to four meters depth," he stated, Friday (7/23).

According to him, its existence was aimed at overcoming flooding or inundation in the surrounding area, such as in Cilangkap, Setu, Lubang Buaya.

"It is done to accommodate water in large quantities when it rains. Moreover, It was previously abandoned and used by residents for illegal paid fishing," he concluded.

Linked News
Popular News indeks
  1. Mothers Attack Cheap Market in Cibubur Urban Village

    access_time02-05-2024 remove_red_eye567 personNurito
  2. LRT Phase 1B Construction Remains Positive

    access_time27-04-2024 remove_red_eye455 personAldi Geri Lumban Tobing
  3. S. Jakarta Residents Enjoy NIK Deactivation Consultation Post Services in Rawajati

    access_time30-04-2024 remove_red_eye350 personTiyo Surya Sakti
  4. Sunny All Day Long in Jakarta

    access_time03-05-2024 remove_red_eye315 personAnita Karyati
  5. Secretariat General Bureau-Information Commission Holds E-Monev Bimtek 2024

    access_time28-04-2024 remove_red_eye284 personAnita Karyati