Contractor Targets to Finish Cilangkap Reservoir Dredging Work in November

Dredging is carried out to four meters depth

The 5-hectare Cilangkap Reservoir dredging work, which is located in RW 01 Cilangkap, Cipayung, East Jakarta has currently touched 30 percent and is targeted to be complete in the forthcoming November.

Clay Dredged from Munjul Reservoir Used to Expand Burial Ground at TPU Bambu Apus

It has two cross sections and is located on the border of Cilangkap and Munjul urban villages.

East Jakarta Water Resources (SDA)'s Maintenance Division Head, Puryanto said, as many as four heavy equipment had been alerted to the location, consisting of three heavy equipment type standard and one unit of long arm.

"Dredging is carried out to four meters depth," he stated, Friday (7/23).

According to him, its existence was aimed at overcoming flooding or inundation in the surrounding area, such as in Cilangkap, Setu, Lubang Buaya.

"It is done to accommodate water in large quantities when it rains. Moreover, It was previously abandoned and used by residents for illegal paid fishing," he concluded.

Linked News
Popular News indeks
  1. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye784 personFakhrizal Fakhri
  2. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye622 personTiyo Surya Sakti
  3. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye424 personAldi Geri Lumban Tobing
  4. Jakarta Newcomers Mostly in Productive Age

    access_time22-04-2026 remove_red_eye383 personAldi Geri Lumban Tobing
  5. East Jakarta Steps Up Services to Simplify Population Registration

    access_time20-04-2026 remove_red_eye355 personNurito